HAPUNA BEACH, WEST HAWAII —
The Department of Land and Natural Resources (DLNR) is continuing
construction work at Hapuna Beach State Recreation Area, that includes
renovations to comfort stations, new accessibility features,
installation of new picnic tables and pathways at pavilions, cesspool
replacement, and other related work.
“To be efficient and shorten the period of inconvenience to park
users, we combined several construction projects to occur
simultaneously. The park and beach will remain open during construction
but some facilities may be temporarily closed until work is finished. We
believe the public will appreciate the finished improvements,” said
Peter Young, DLNR chairperson.
“Portable toilets will be provided when any comfort station is closed
for renovation. The contractor has been instructed to work on one
comfort station and one picnic pavilion at a time, to minimize
inconvenience to park users. Appropriate safety measures will be applied
during construction,” he said.
Isemoto Contracting Co. is currently renovating the park's three
comfort stations (north beach, south beach, and parking area
facilities); north and south picnic pavilions; A-frame rental cabin and
kitchen pavilion area; maintenance base yard; and office trailer areas.
Planned renovations are as follows:
-- Comfort stations will be fully renovated and made accessible.
Improvements will include: new floor and wall tiles; new toilets and
urinals, new lavatories, new changing benches, grab bars; signage; and
connecting pathway improvements.
-- Park picnic pavilions will have new accessible picnic tables and
pathway improvements.
-- Improvements to make Cabin #6 and kitchen accessible consist of:
cabin entrance improvements, installation of accessible picnic table,
kitchen counter, sink, and range improvements, accessible toilets,
lavatories, showers and changing areas.
-- Accessible entrance, pathway and restroom improvements at the
maintenance base yard.
-- Accessible parking and entry improvements at the office trailer.
Construction total cost is $669,549. Project completion date is
approximately June - July 2006
Meanwhile, contractor Site Engineering, Inc. has nearly completed
previously started projects including: resurfacing and striping of the
upper parking lot; repaving and drainage improvements to the South Beach
road, accessible parking stalls and access aisles; striping and signage
and other improvements. Construction cost is $253,728.
Also, the contractor has completed construction at the Wailea section
of the park. Improvements include access road paving, parking
improvements, and other park improvements. Contractor: Site Engineering,
Inc. Construction cost is $232,076.
Starting next month, work will begin on installation of new septic
systems for the north, south, and parking area comfort stations, to
replace the park’s large capacity cesspool as required by agreement with
the Environmental Protection Agency. Contractor is Big Island
Excavating, LLC. The project will cost $526,500 and be completed in
about four months. Portable toilets will be provided if any comfort
stations are closed for a prolonged period.
# # #